Installation of automatic wastewater monitoring at My Phuoc 1.3 Industrial Park Wastewater Treatment Plant
Supply and installation of water environment monitoring system for the wastewater treatment plant in My Phuoc 1.3 Industrial Park Wastewater Treatment Plant - Investor: INDUSTRIAL DEVELOPMENT AND INVESTMENT CORPORATION (BECAMEX IDC)
28th May 2017 Thanh Cong Automation Co., Ltd signed a contract to supply, install, and connect complete data transmitted to the Department of Natural Resources and Environment and guide the operation of the automatic monitoring system of wastewater quality after treatment. management of " My Phuoc 1.3 Industrial Park Wastewater Treatment Plant ".
Measurement parameters: COD, TSS, pH, temperature, and output open channel flow.
The device connected to the DCS system and the device that transmits data to the monitoring center of the Department of Natural Resources and Environment complies with Circular 24/2017/ Circular of the Ministry of Natural Resources and Environment on technical regulations on environmental monitoring.
Supply and installation of electrical cabinets, control equipment, and data import and export monitoring system - Investor: Vedan Vietnam limited joint-stock company.
Supply and installation of water environment monitoring system for the wastewater treatment plant in Bau Bang Industrial Park - Investor: INDUSTRIAL DEVELOPMENT AND INVESTMENT CORPORATION (BECAMEX IDC)